www.McqFinder.in
Home
MCQ
Search
Free Apps
Important
Study Groups
Contact Us
Policy
Home
MCQ
Objective Questions
ITI
Draughtsman Civil
Draughtsman Civil Set-1
Estimation
Estimation MCQ with Answers
16)
What is the unit for ridges, valleys, gutters in M.K.S system?
metre
sq.m
cu.m
Nos.
Answer
Answer is:
metre
17)
What is the unit for flooring in MKS system?
m
sq.m
cu.m
Nos.
Answer
Answer is:
sq.m
18)
What is the minimum lead for earth work excavation?
10 m
20 m
30 m
50 m
Answer
Answer is:
30 m
19)
What is the minimum lift for earthwork excavation?
1 m
1.5 m
2.0 m
3.0 m
Answer
Answer is:
1.5 m
20)
What is the measuring unit for soling layer?
m
sq.m
cu.m
Nos.
Answer
Answer is:
sq.m
PREV
4
NEXT
1
2
3
4
5
6
7